The article presents a simple F# DSL for software estimation and project planning. It uses English-like statements to define a project, add resources, group tasks, assign durations, and then generate a Microsoft Project plan.
Reading notes #
- The article defines a DSL as a way to express domain-specific logic in English instead of a programming language.
- The example domain is software estimation, with a real-world version already used at the author’s company.
- The attached code is a single .fs file and requires Project 2007 to run.
- The problem described is estimating software work from an RFP by breaking a project into tasks, durations, resources, and milestones.
- The DSL is meant to save time compared with drawing and rearranging a Gantt chart in Microsoft Project.
- It also lets business logic and validation rules be embedded in the planning procedure.
- The target users are project managers who may not know programming but can work with a DSL.
- The article presents F# as a good choice because it is a first-class .NET language and can be used to build the needed infrastructure.
- The first statement shown defines a project name and start date, and it maps to a
Projecttype with mutable fields. - The DSL keeps one project in a global variable called
my_project. - A
projectfunction initializes the project name, empty resource and group lists, and parses the start date. - Resources are modeled with a
Resourcetype containing name, position, and rate. - A
resourcestatement creates a resource and prepends it to the project’s resource list. - The article notes that list items end up in reverse order and are later reversed when needed.
- A
groupstatement links a task group to a named resource using string lookup over the project’s resource list. - Tasks are modeled with a
Tasktype containing name and duration. - Time units are represented by constants such as hours, days, weeks, and months so that
task ... takes ...reads fluently. - The
taskfunction formats duration values for Project and adds each task to the current group. - The current task is found as the head of the list because new tasks are prepended.
- The
preparefunction creates a Project application, adds the project, copies resources, creates group tasks, and links task predecessors. - The article ends with a complete sample script that defines resources, groups, tasks, and finishes with
prepare my_project.